Temporary WaterDam for new slipway | Temporary Dams

Temporary WaterDam for new slipway

Project Description

Client: Lindum Group

Location: Peterborough

Project Duration: 6 Weeks

Project Details:

Murlac was contacted by The Lindum Group to provide a dry working area to facilitae the repair and extension of an existing slipway.The water depth was suitable for a 1.2m high water filled temporary dam designed to control up to 90cm of water was successfully installed and removed by Murlacs in-house installation team.The water filled dam was the chosen option for the customer due to its low environmental impact, ease of installation and removal along with the cost savings compared to other temporary cofferdams.A total of 40 linear metres of water dam were installed for a project duration of 6 weeks.For more information about our range of temporary damming solutions please contact us